Week 06 commitment
3 parts434 words
6 checkboxes β tick them, they save to the file
State: UNCONFIRMED. Owner: Peter Ciancaglini. Specification
Start date: not set. End date: not set. Available hours: confirm (planned ceiling 10). Primary outcome: human gold standard. Minimum that keeps the next gate alive: 50 gold JSONs.
0101
Deliverables to commit
01
Deliverables to commit
-
annotation-guidelines.md: Each annotated value has a source sentence and document locator. -
annotation-progress.csv: Completed and incomplete records are counted, with no model labels passed off as human gold. -
annotator-brief.md: Gold target is met or shortage logged; external acceptance is evidenced separately. - Bounded learning exercise and personal teach-back.
- Evidence-backed branding and opportunity pack.
- Sunday review and next physical action.
0202
Proposed calendar
02
Proposed calendar
| Day | Minutes | Physical action / outcome | Actual slot | Done |
|---|---|---|---|---|
| Mon | 90 | Write field-by-field definitions, units, examples, ambiguity rules and adjudication procedure; annotate the first 15 papers while timing the first three. | Not set | [ ] |
| Tue | 90 | Notes; Rosalind 5-8 | Not set | [ ] |
| Wed | 90 | Annotate the next 20 target papers independently of model outputs; revise guidelines with versioned ambiguity decisions. Last ten minutes: optional note. | Not set | [ ] |
| Thu | 90 | Notes; a Bayesian update by hand Include relevant founder-paper work within this block. | Not set | [ ] |
| Fri | 90 | Finish the 50-paper target and prepare two annotator invitations for 30 overlapping papers; schedule blinded handoff and return by week 10. | Not set | [ ] |
| Sat | 90 | Resolve critical spillover; long-form draft if due; sandbox only if done. | Not set | [ ] |
| Sun | 60 | Build log, evidence, gap review, next actions. | Not set | [ ] |
0303
Dependency and capacity check
03
Dependency and capacity check
- Missing essential inputs: not yet inspected.
- Human/external dependency, owner and expected date: not yet inspected.
- Week-specific constraint: Fifty papers in three build blocks is a feasibility risk. Project time from the first three; use Saturday and request a scope/schedule decision if needed. Never fabricate completion or replace the second human with an LLM.
- Existing session authorization for external actions or spending: not assessed; local planning only at scaffold creation.
- Scope to cut first: optional polish/additional examples; preserve scientific validity.
- If the forecast exceeds available time: record a concrete reduced scope or revised delivery proposal before committing.
Peter's commitment / adjustments: pending. Reviewing model and date: pending.