# Week 26 commitment

State: UNCONFIRMED. Owner: Peter Ciancaglini. [Specification](./specs.md)

Start date: not set. End date: not set. Available hours: confirm (planned ceiling 10).
Primary outcome: trialkit plate module.
Minimum that keeps the next gate alive: Generate one plate report with correct control handling, replicate identities and explicit fit/QC failures.

## Deliverables to commit

- [ ] `plate-schema.md`: Generate one plate report with correct control handling, replicate identities and explicit fit/QC failures.
- [ ] `plate-fit-report.md`: At least one verified public example per implemented model has identifiable fits and uncertainty.
- [ ] `plate-qc-checklist.md`: Bad controls, insufficient points and failed fits appear in the output.
- [ ] Bounded learning exercise and personal teach-back.
- [ ] Evidence-backed branding and opportunity pack.
- [ ] Sunday review and next physical action.

## Proposed calendar

| Day | Minutes | Physical action / outcome | Actual slot | Done |
|---|---:|---|---|---|
| Mon | 90 | Specify plate layout and metadata mapping for 96/384-well exports with blanks, controls and replicate IDs. | Not set | [ ] |
| Tue | 90 | One concise applied note, a worked decision/example and unresolved questions. | Not set | [ ] |
| Wed | 90 | Fit dose-response/growth/kinetics examples with model diagnostics, parameter bounds and explicit failure reports. Last ten minutes: optional note. | Not set | [ ] |
| Thu | 90 | One concise applied note, a worked decision/example and unresolved questions. Include relevant founder-paper work within this block. | Not set | [ ] |
| Fri | 90 | Add Z-prime/control QC and a report with data provenance; scope MIC to validated rules if applicable. | Not set | [ ] |
| Sat | 90 | Resolve critical spillover; long-form draft if due; sandbox only if done. | Not set | [ ] |
| Sun | 60 | Build log, evidence, gap review, next actions. | Not set | [ ] |

## Dependency and capacity check

- Missing essential inputs: not yet inspected.
- Human/external dependency, owner and expected date: not yet inspected.
- Week-specific constraint: Do not implement every assay family in one block without reliable validation. Start with one complete path; no biological replicate inflation or unsupported potency claims.
- Existing session authorization for external actions or spending: not assessed; local planning only at scaffold creation.
- Scope to cut first: optional polish/additional examples; preserve scientific validity.
- If the forecast exceeds available time: record a concrete reduced scope or revised delivery proposal before committing.

Peter's commitment / adjustments: pending.
Reviewing model and date: pending.